Instructions: G743™CW-2024 Continuation Sheet for Cost of the Work Design-Build Projects

Completing G743CW-2024.

Heading. This information should be completed in a manner consistent with similar information on AIA Document G742CW-2024 or AIA Document G742GMP-2024.

Columns A and B. These columns should be completed by identifying the various portions of the Project and their scheduled values consistent with the schedule of values submitted to the Architect at the commencement of the Project or as subsequently adjusted. The breakdown may be by sections of the Work or by Subcontractors and should remain consistent throughout the Project. Multiple pages should be used when required.

Column C1. Column C1 should be subtotaled at the bottom when more than one page is used and totaled on the last page. For projects with a Guaranteed Maximum Price, the total of column C should be the total Guaranteed Maximum Price at the outset of the Project. For projects without a Guaranteed Maximum Price, the total should be the original control estimate of the Cost of the Work.

Column C2 & C3. Column C2 should be used to show any changes in the scheduled value of each portion of the work from previous applications for payment. Column C3 should be used to identify any changes in the scheduled value for each portion of the work that occurred during this period.

Column C4. Column C4 should be used to show the current scheduled value of each portion of the work as of the current application for payment.

Column D. Enter in this column the amount of completed Work covered by the previous application (columns D & E from the previous application). Values from column F (Materials Presently Stored) from the previous application should not be entered in this column.

Column E. Enter here the value of Work completed at the time of this application, including the value of materials incorporated in the project that were listed on the previous application under Materials Presently Stored (column F).

Column F. Enter the value of Materials Presently Stored for which payment is sought. The total of the column must be recalculated at the end of each pay period. This value covers both materials newly stored for which payment is sought and materials previously stored which are not yet incorporated into the Project. Mere payment by the Owner for stored materials does not result in a deduction from this column. Only as materials are incorporated into the Project is their value deducted from this column and incorporated into column E (Work Completed—This Period.)

Column G. Enter the total of columns D, E, and F. Calculate the percentage completed by dividing column G by column C.

Column H. Enter the difference between column C (Scheduled Value) and column G (Total Completed and Stored to Date).

Column I. This column is normally used only for contracts where variable retainage is permitted on a line-item basis. It need not be completed on projects where a constant retainage is withheld from the overall contract amount.

Change Orders. Although Change Orders could be incorporated by changing the schedule of values each time a Change Order is added to the Project, this is not normally done. Usually, Change Orders are listed separately, either on their own G743®CW form or at the end of the basic schedule. The amount of the original contract adjusted by Change Orders is to be entered in the appropriate location on the G742GMP form, if applicable.

Change Directives. Amounts not in dispute that have been included in Change Directives should be incorporated into one or more Change Orders. Amounts remaining in dispute should be dealt with according to Section 6.3 of AIA Document A141-2024 or Section 7.3 of AIA Document A141PDB-2024.

Notes.

Modifications. Particularly with respect to professional or contractor licensing laws, building codes, taxes, monetary and interest charges, arbitration, indemnification, format and font size, AIA Contract Documents may require modification to comply with state or local laws. Users are encouraged to consult an attorney before completing or modifying a document.

Reproductions. This document is a copyrighted work and may not be reproduced or excerpted from without the express written permission of the AIA. There is no implied permission to reproduce this document, nor does membership in The American Institute of Architects confer any further rights to reproduce this document. For more information, see the document footer and the AIA Contract Documents® Terms of Service.

 

Was this article helpful?
0 out of 0 found this helpful

Articles in this section

See more
For document related questions:
For technical support:
Our helpline hours:
8:30am - 6:00pm EST Monday to Friday