Instructions: G703S®–2017, Continuation Sheet Contractor-Subcontractor Version

 

Synopsis. 

AIA Document G702S™–2017, Application and Certificate for Payment, and G703S®–2017, Continuation Sheet, provide convenient and complete forms on which the subcontractor can apply for payment. The forms require the subcontractor to show the status of the contract sum to date, including the total dollar amount of the work completed and stored to date, the amount of retainage (if any), the total of previous payments, a summary of change orders, and the amount of current payment requested. AIA Document G703S®-2017 breaks the contract sum into portions of the work in accordance with a schedule of values prepared by the subcontractor as required by the general conditions. For all document details and a record of changes, see the summary  »

Note: The AIA does not publish a standard schedule of values form.

 

Using G703S®–2017.

Heading. This information should be completed in a manner consistent with similar information on AIA Document G702S, Application and Certificate for Payment, Contractor-Subcontractor Version.

Columns A, B, and C. These columns should be completed by identifying the various portions of the Project and their scheduled values consistent with the schedule of values submitted to the Architect at the commencement of the Project or as subsequently adjusted. The breakdown may be by sections of the Work or by Subcontractors and should remain consistent throughout the Project. Multiple pages should be used when required. Column C should be subtotaled at the bottom when more than one page is used and totaled on the last page. Initially, this total should equal the original Contract Sum. The total of column C may be adjusted by Change Orders during the Project.

Column D. Enter in this column the amount of completed Work covered by the previous application (columns D & E from the previous application). Values from column F (Materials Presently Stored) from the previous application should not be entered in this column.

Column E. Enter here the value of Work completed at the time of this application, including the value of materials incorporated in the project that were listed on the previous application under Materials Presently Stored (column F).

Column F. Enter here the value of Materials Presently Stored for which payment is sought. The total of the column must be recalculated at the end of each pay period. This value covers both materials newly stored for which payment is sought and materials previously-stored which are not yet incorporated into the Project. Mere payment by the Owner for stored materials does not result in a deduction from this column. Only as materials are incorporated into the Project is their value deducted from this column and incorporated into column E (Work Completed—This Period.)

Column G. Enter here the total of columns D, E and F. Calculate the percentage completed by dividing column G by column C.

Column H. Enter here the difference between column C (Scheduled Value) and column G (Total Completed and Stored to Date).

Column I. This column is normally used only for contracts where variable retainage is permitted on a line-item basis. It need not be completed on projects where a constant retainage is withheld from the overall contract amount.

Change Orders. Although Change Orders could be incorporated by changing the schedule of values each time a Change Order is added to the Project, this is not normally done. Usually, Change Orders are listed separately, either on their own G703 form or at the end of the basic schedule. The amount of the original contract adjusted by Change Orders is to be entered in the appropriate location on the G702 or G732™ form, whichever is applicable.

Construction Change Directives. Amounts not in dispute that have been included in Construction Change Directives should be incorporated into one or more Change Orders. Amounts remaining in dispute should be dealt with according to Section 7.3 of AIA Document A201® or Section 7.3 of AIA Document A232™.

The following is an example of a Continuation Sheet for work in progress. Please note that dollar amounts shown below are for illustrative purposes only, and are not intended to reflect actual construction costs.

Example of a continuation sheet

 

On-demand video on completing payment applications and change orders »

 

Important.

Modifications. Particularly with respect to professional or contractor licensing laws, building codes, taxes, monetary and interest charges, arbitration, indemnification, format and font size, AIA Contract Documents may require modification to comply with state or local laws. Users are encouraged to consult an attorney before completing or modifying a document.

Reproductions. This document is a copyrighted work and may not be reproduced or excerpted from without the express written permission of the AIA. There is no implied permission to reproduce this document, nor does membership in The American Institute of Architects confer any further rights to reproduce this document. For more information, see the document footer and the AIA Contract Documents® Terms of Service.

Was this article helpful?
7 out of 21 found this helpful

Articles in this section

See more
For document related questions:
For technical support:
Our helpline hours:
8:30am - 6:00pm EST Monday to Friday