Summary: G701™–2017, Change Order

 

Content. 

Synopsis

Purpose

Changes from previous edition

 

Synopsis.

AIA Document G701-2017 is used for implementing changes in the work agreed to by the owner, contractor, and architect. Execution of a completed G701 indicates agreement upon all terms of the change, including any changes in the contract sum (or guaranteed maximum price) and contract time. The form allows for signatures of the owner, architect, and contractor, and for a description of the change. For use and execution of a document, see its instructions  »

 

Purpose. 

AIA Document G701–2017 is for implementing changes in the Work agreed to by the Owner, Contractor, and Architect. Execution of a completed G701 indicates agreement upon all the terms of the change, including any changes in the Contract Sum (or Guaranteed Maximum Price) and Contract Time. 

 

Changes from the previous edition. 

Description of Change in the Contract. Insert a detailed description of the change or reference specific exhibits describing, in detail, the change to be made in the Contract by this Change Order. Include any drawings, specifications, documents or other supporting data to clarify the scope of the change. 

Was this article helpful?
5 out of 25 found this helpful

Articles in this section

See more
For document related questions:
For technical support:
Our helpline hours:
8:30am - 6:00pm EST Monday to Friday