G732™ – 2019, Application and Certificate for Payment, Construction Manager as Adviser Edition
Synopsis.
AIA Document G732–2019 serves the same purpose as AIA Document G702™–1992. The standard form AIA Document G703™–1992, Continuation Sheet, is appropriate for use with G732–2019.
For all document details and a record of changes, see the summary »
Using G732–2019.
After the Contractor has completed AIA Document G703, Continuation Sheet, summary information should be transferred to AIA Document G732–2019, Application and Certificate for Payment, Construction Manager as Adviser Edition. The Contractor should sign G732, have it notarized and submit it, together with G703, to the Construction Manager and Architect. The Construction Manager and Architect should review G732 and G703 and, if they are acceptable, complete the Certificate for Payment on G732. The Construction Manager and Architect may certify a different amount than that applied for pursuant to Sections 9.5 and 9.6 of AIA Document A232–2019. They should then initial all figures on G732 and G703 that have been changed to conform to the amount certified and attach an explanation. The completed G732 and G703 should be forwarded to the Owner.
Completing G732–2019.
Heading. This information should be completed to be consistent with similar information on AIA Document G732–2019, Application and Certificate for Payment, Construction Manager as Adviser Edition.
Columns A, B, and C. These columns should be completed by identifying the various portions of the Project and their scheduled value consistent with the schedule of values submitted at the commencement of the Project or as subsequently adjusted. The breakdown may be by sections of the Work or by Subcontractors and should remain consistent throughout the Project. Multiple pages should be used when required.
Column C. Should be subtotaled at the bottom when more than one page is used and totaled on the last page. Initially, this total should equal the original Contract Sum. The total of column C may be adjusted by Change Orders during the Project.
Column D. Enter in this column the amount of completed work covered by the previous application (columns D & E from the previous application). Values from column F (Materials Presently Stored) from the previous application should not be entered in this column.
Column E. Enter here the value of Work completed at the time of this application, including the value of materials incorporated into the project which were listed on the previous application under Materials Presently Stored (column F).
Column F. Enter here the value of Materials Presently Stored for which payment is sought. The total of the column must be recalculated at the end of each pay period. This value covers both materials newly stored for which payment is sought and materials previously stored which are not yet incorporated into the Project. Mere payment by the Owner for stored materials does not result in a deduction from this column. Only as materials are incorporated into the Project is their value deducted from this column and incorporated into column E (Work Completed – This Period).
Column G. Enter here the total of columns D, E and F. Calculate the percentage completed by dividing column G by column C.
Column H. Enter here the difference between column C (Scheduled Value) and column G (Total Completed and Stored to Date).
Column I. This column is normally used only for contracts where variable retainage is permitted on a line-item basis. It need not be completed on projects where a constant retainage is withheld from the overall contract amount.
Change Orders and Construction Change Directives. The amount of the original contract, adjusted by Change Orders and amounts authorized for Construction Change Directives as reflected in line 2, is to be entered on line 3 of the G732 form.
Making payment.
The Owner should make payment directly to the Contractor based on the amount certified by the Construction Manager and Architect on AIA Document G732–2019, Application and Certificate for Payment, Construction Manager as Adviser Edition. The completed form contains the name and address of the Contractor. Payment should not be made to any other party unless specifically indicated on G732.
Important.
Modifications. Particularly with respect to professional or contractor licensing laws, building codes, taxes, monetary and interest charges, arbitration, indemnification, format and font size, AIA Contract Documents may require modification to comply with state or local laws. Users are encouraged to consult an attorney before completing or modifying a document.
Reproductions. This document is a copyrighted work and may not be reproduced or excerpted from without the express written permission of the AIA. There is no implied permission to reproduce this document, nor does membership in The American Institute of Architects confer any further rights to reproduce this document. For more information, see the document footer and the AIA Contract Documents® Terms of Service.