AIA Contract Documents does not provide a certificate of final completion or project closeout forms. However, it offers several certificates for substantial completion, including G704-2017, G734-2019, and G744-2014 for various project types, such as design-build and construction manager-adviser. There is no subcontractor variation of the G704-2017 form.

 

Even though AIA Contract Documents does not publish a certificate of final completion or project closeout forms, multiple forms for substantial completion are published:

G704–2017, Certificate of Substantial Completion

G734–2019, Certificate of Substantial Completion, Construction Manager-Adviser Edition

G744™–2014, Certificate of Substantial Completion for a Design-Build Project

Please note: AIA Contract Documents does not publish a Subcontractor variation of AIA Document G704–2017, Certificate of Substantial Completion.

Was this article helpful?
5 out of 19 found this helpful

Articles in this section

See more
For document related questions:
For technical support:
Our helpline hours:
8:30am - 6:00pm EST Monday to Friday