Instructions: G743™-2024 Continuation Sheet for Design-Build Projects

Completing G743–2024

Heading: This information should be completed in a manner consistent with similar information on AIA Document G742-2024, Application and Certificate for Payment for a Design-Build Project.

Columns A, B and C: These columns should be completed by identifying the various portions of the Project and their scheduled values consistent with the schedule of values submitted to the Owner at the commencement of the Project or as subsequently adjusted. The breakdown may be by sections of the Work or by the Architect, Consultants, Contractors, or Subcontractors and should remain consistent throughout the Project. Multiple pages should be used when required.

Column C should be subtotaled at the bottom when more than one page is used and totaled on the last page. Initially, this total should equal the original Contract Sum. The total of column C may be adjusted by Change Orders during the Project.

Column D: Enter in this column the amount of completed Work covered by the previous application (columns D & E from the previous application). Values from column F (Materials Presently Stored) from the previous application should not be entered in this column.

Column E: Enter here the value of Work completed at the time of this application, including the value of materials incorporated in the project that were listed on the previous application under Materials Presently Stored (column F).

Column F: Enter here the value of Materials Presently Stored for which payment is sought. The total of the column must be recalculated at the end of each pay period. This value covers both materials newly stored for which payment is sought and materials previously stored which are not yet incorporated into the Project. Mere payment by the Owner for stored materials does not result in a deduction from this column. Only as materials are incorporated into the Project is their value deducted from this column and incorporated into column E (Work Completed—This Period.)

Column G: Enter here the total of columns D, E and F. Calculate the percentage completed by dividing column G by column C.

Column H: Enter here the difference between column C (Scheduled Value) and column G (Total Completed and Stored to Date).

Column I: This column is normally used only for contracts where variable retainage is permitted on a line-item basis. It need not be completed on projects where a constant retainage is withheld from the overall contract amount.

Change Orders. Although Change Orders could be incorporated by changing the schedule of values each time a Change Order is added to the Project, this is not normally done. Usually, Change Orders are listed separately, either on their own G743 form or at the end of the basic schedule. The amount of the original contract adjusted by Change Orders is to be entered in the appropriate location on the G742.

Change Directives. Amounts not in dispute that have been included in Change Directives should be incorporated into one or more Change Orders. Amounts remaining in dispute should be dealt with according to Section 6.3 of AIA Document A141-2024 or Section 7.3 of AIA Document A141PDB-2014.

The following is an example of a Continuation Sheet for work in progress. Please note that dollar amounts shown below are for illustrative purposes only and are not intended to reflect actual construction costs

A B C D E F G H I  
ITEM NO. DESCRIPTION OF WORK SCHEDULED VALUE WORK COMPLETED MATERIALS PRESENTLY STORED
(Not in D or E)

TOTAL COMPLETED AND STORED TO DATE

(D + E + F)

%

(G ÷ C)

BALANCE  TO   FINISH

(C − G)

RETAINAGE (If variable rate)  

FROM PREVIOUS APPLICATION

(D + E)

THIS PERIOD  
 
 
 
1  MOBILIZATION 5,000 5,000 0 0 5,000 100 0    
2  STUMP REMOVAL 5,000 5,000 0 0 5,000 100 0  
3  EARTH WORK 15,000 10,000 5,000 0 15,000 100 0  
4  LOWER RETAINING WALL 10,000 0 5,000 0 5,000 50 5,000  
5  CURBS & MISC. CONC. 5,000 0 0 0 0 0 5,000  
6  PAVING, UPPER DRIVE 20,000 0 0 0 0 0 20,000  
7  PAVING, LOWER DRIVE 20,000 0 0 0 0 0 20,000  
8  PAVERS 20,000 0 0 10,000 10,000 50 10,000  
9  BRICK WORK 5,000 0 0 0 0 0 5,000  
10                  
11 GRAND TOTAL 105,000 20,000 10,000 10,000 40,000   65,000    

 

Notes

Related Documents. AIA Document G743-2024, Continuation Sheet for a Design-Build Project, is to be used in conjunction with AIA Document G742-2024, Application and Certificate for Payment for a Design-Build Project. These documents are designed for use on Design-Build Projects. Procedures for their use are covered in AIA Document A141–2024, Standard Form of Agreement Between Owner and Design-Builder.

Use of Current Documents. Prior to using any AIA Contract Document, users should consult www.aia.org or a local AIA component to verify the most recent edition.

Reproductions. This document is a copyrighted work and may not be reproduced or excerpted from without the express written permission of the AIA. There is no implied permission to reproduce this document, nor does membership in The American Institute of Architects confer any further rights to reproduce this document. For more information, see the document footer and the AIA Contract Documents® Terms of Service.

 

Was this article helpful?
0 out of 0 found this helpful

Articles in this section

See more
For document related questions:
For technical support:
Our helpline hours:
8:30am - 6:00pm EST Monday to Friday