These commonly used terms refer to the following documents, which are tailored to be used together:
G702–1992, Application and Certificate for Payment
G703–1992, Continuation Sheet
We also have "cost-plus" versions where the basis of payment is the cost of the work plus a fee:
G702CW–2021, Application and Certificate for Payment for Cost of the Work Projects without a Guaranteed Maximum Price
G702GMP–2021, Application and Certificate for Payment for Cost of the Work Projects with a Guaranteed Maximum Price
G703CW–2021, Continuation Sheet for Cost of the Work Projects
In addition, we also have versions for a subcontractor to apply to a contractor:
G702S–2017, Application and Certificate for Payment, Subcontractor Variation
G703S–2017, Continuation Sheet, Subcontractor Variation.
Any of these could be appropriate to use on projects where the Construction Manager is also the Constructor (CMc) with agreements A133–2019 or A134–2019.
In a project with a Construction Manager as Adviser (CMa), the following document should be used instead:
G732–2019, Application and Certificate for Payment, CMa Edition
G703–1992, Continuation Sheet may be used in this situation.
For a Design-Build project, use:
G742–2015, Application and Certificate for Payment for a Design-Build Project
G743–2015, Continuation Sheet for a Design-Build Project
Versions of these documents are available for use by the Design-Builder, Contractor, and Subcontractors.